N3 closed 35 hours near Hammarsdale as SANRAL demolishes bridge

N3 closed 35 hours near Hammarsdale as SANRAL demolishes bridge

By: OrePulse

A 35-hour closure of South Africa's N3 highway between Cato Ridge and Hammarsdale disrupted freight traffic over the weekend on the main road corridor linking the Port of Durban with Gauteng and other inland industrial centers.

The South African National Roads Agency (SANRAL) shut both directions of the route from 18:00 on Saturday, November 14, to 05:00 on Monday, November 16, so crews could demolish the Harrison East Bridge, an overpass also known locally as the D157 bridge. The work forms part of a broader project to widen the N3 corridor.

While the road was closed, Durban-bound traffic coming from Pietermaritzburg was routed off the highway at Cato Ridge onto the R103 and the MR385, rejoining the N3 at Hammarsdale; vehicles traveling in the opposite direction followed the same detour in reverse. SANRAL urged motorists, and heavy-vehicle operators in particular, to plan around the diversion, and it encouraged freight companies to weigh delaying departures or arranging alternative staging for the duration of the works.

SANRAL said building the new bridge on the site will take roughly two years once construction gets underway, so further intermittent disruption along the corridor is likely as that longer rebuild proceeds in stages.

The N3 is South Africa's principal road link between its busiest container port and the industrial and commercial hub of Gauteng, carrying a large share of the country's import and export cargo by truck. Weekend and overnight closures of this kind are the agency's usual way of carrying out structural work on the route while limiting the impact on weekday traffic volumes.