Wison breaks ground on $4 billion ADNOC Gas train at Habshan

Wison breaks ground on $4 billion ADNOC Gas train at Habshan

By: OrePulse

Construction has started on a new gas processing train at ADNOC Gas's Habshan complex in Abu Dhabi after Wison Engineering held a groundbreaking ceremony there, launching the second phase of the state-controlled producer's Rich Gas Development program, the companies said.

ADNOC Gas awarded Wison the engineering, procurement and construction contract for the train in August, valued at $3.9 billion. Including an associated 220-kilovolt switching station, the total value of the award comes to about $4.04 billion, which Wison described as its largest EPC project to date and among the bigger single awards handed out so far under the wider Rich Gas Development program.

As main contractor, Wison will deliver the new processing train, which includes gas treatment units and deep natural-gas-liquids recovery facilities. ADNOC Gas said the addition will expand large-scale processing capacity at Habshan and give the company greater operational flexibility, while also supporting growth in the United Arab Emirates' downstream and petrochemical industries. Engineering, procurement and site-preparation work had already been under way since the project was launched, and on-site construction activity is now set to increase following the groundbreaking.

Wison Chief Executive Hongliang Zhou said the groundbreaking "marks the project's transition into full construction." He said the company's priorities going forward would center on keeping the job safe, holding to quality standards and executing in a disciplined manner alongside ADNOC Gas and its partners. Wison said the contract adds to its history of major EPC work across the Middle East and that it would lean on its combined engineering, procurement and construction know-how and its worldwide network of suppliers to carry it out.

The new train forms part of the second phase of ADNOC Gas's Rich Gas Development program, which follows an initial phase the company sanctioned last year. That first phase, backed by roughly $5 billion in awarded contracts, covers upgrades and debottlenecking work at the Asab, Buhasa and Habshan onshore facilities and at the Das Island offshore liquefaction plant, with the broader program aimed at developing new gas reservoirs, improving the UAE's self-sufficiency in gas supply, and providing additional feedstock for the petrochemical sector. ADNOC Gas has indicated that further phases at Habshan and at Ruwais are being lined up for future investment decisions.

The first-phase contracts were split across three separate EPCM awards. Wood took the largest, worth about $2.8 billion, to upgrade and debottleneck Habshan's existing gas-processing units and the pipelines feeding them. Petrofac and Kent shared the remaining tranches, worth a combined roughly $2.3 billion, for work at Das Island, Asab and Buhasa; Petrofac's share runs the engineering, procurement and construction effort for a newly built inlet facility and for a pair of gas-dehydration and compression trains sized at 420 million standard cubic feet a day apiece, plus upgrades to the facilities that gather and move raw gas.

ADNOC Gas Chief Executive Fatema Al Nuaimi linked the broader Rich Gas Development program, when the first phase was sanctioned last year, to a target of lifting the company's earnings before interest, tax, depreciation and amortization by more than 40% between 2023 and 2029. Habshan is one of ADNOC's principal onshore gas-processing hubs, and successive phases of the program have continued to add capacity there even as the company has pushed other elements of the project toward Das Island, Asab, Buhasa and, eventually, Ruwais.

Taken together, the two phases disclosed so far point to a program running into the billions of dollars across several of ADNOC Gas's core onshore and offshore sites, with Habshan drawing contracts from two different EPC contractors within roughly a year of each other. ADNOC Gas has not disclosed a combined timeline or completion date covering both phases of the program.