NNPC says AKK gas pipeline 95% complete, Abuja gas targeted by year-end

NNPC says AKK gas pipeline 95% complete, Abuja gas targeted by year-end

By: OrePulse

Nigeria's state oil company says its long-delayed Ajaokuta-Kaduna-Kano gas pipeline is now 95% finished, with Group Chief Executive Bashir Ojulari telling the News Agency of Nigeria in Abuja that the line should start delivering gas to the capital before the end of this year.

Ojulari said the work still outstanding involves finishing a handful of stations along the route and connecting offtake points that will carry gas from the mainline out to end-users. "The remaining five per cent has to do with some of the stations," he said, pointing to Abuja as the first destination. "We are hoping that before the end of the year, we will get the gas to Abuja," he said, adding that Kaduna and Kano should follow in 2027. He also referred to eventual extensions toward Maiduguri and Sokoto, without giving a timeframe for either.

NNPC Ltd has raised $1.5 billion for the pipeline, Ojulari said, basing the financing on the volumes of gas the line is projected to carry once complete. He did not identify the lenders involved, describe how the financing is structured, or give a total cost figure for the project as a whole.

The pipeline runs 614 kilometers from Ajaokuta in Kogi State to Kano, with a 40-inch diameter and a series of intermediate and terminal gas facilities along its length. Ojulari said the gas reaching Abuja is intended to serve power generation, including the city's power plant, along with data centres, industrial hubs and factories.

He also tied the project to the availability of compressed natural gas across northern Nigeria, saying supply would improve as more connections are built northward. "As we move north and we build those connections, the CNG availability will increase phenomenally," he said, adding that reaching Maiduguri and Sokoto through the pipeline would be more practical than trucking gas in from Port Harcourt in the south.

The interview did not include gas volume or capacity figures for the line, a breakdown of how the $1.5 billion in financing would be spent, names of the stations still being completed, or a timeline for finishing them. Nor did it address whether the Abuja, Kaduna and Kano delivery targets are tied to any binding commitment, or describe any government or regulatory response to the project's progress.

The project has featured in Nigerian officials' public remarks before: Ojulari gave a similar timeline for first gas reaching Abuja by the end of the year in comments made earlier this month at the ADIPEC conference. Friday's interview adds the specific 95% completion figure and the $1.5 billion financing disclosure to that earlier account, though it leaves unclear whether the financing figure was being stated publicly for the first time.