Mauritania's SOMELEC cancels deal for 8 Nouakchott power plants

Mauritania's SOMELEC cancels deal for 8 Nouakchott power plants

By: OrePulse

Mauritania's state power utility, the Société Mauritanienne d'Électricité (SOMELEC), has canceled a contract to build two new power plants in the capital, Nouakchott, and rehabilitate six existing ones, citing persistent, fundamental failures by the contractor to meet its obligations.

The cancellation of contract No. 01/CMI/2026 was conveyed in a letter to the consortium led by CTM Construction Company, dated November 12, 2026. The contract, awarded to CTM on January 22, 2026 in partnership with Turnkey Solution SARL and Electromechanical & Communication Engineers, covered two new power plants in southern and northern Nouakchott plus the rehabilitation of six existing plants, over a 16-month term; an addendum to the contract was signed on March 15, 2026.

SOMELEC said actual physical progress on the works had reached only 3.5% as of October 15, 2026, even though 27% of the 16-month contract period had already elapsed. The utility said it had issued two formal warnings to CTM, on September 4 and September 28, 2026, giving the company legal grace periods to correct the violations, but that CTM neither took the necessary corrective steps nor presented a clear plan to make up the delay.

According to SOMELEC, the contractor's own monthly progress reports had put completion at 5.2%, while the project's consulting engineer separately estimated actual progress at about 3.5%. SOMELEC also said a worksite had never actually been established at the southern plant, despite the site having been handed to the contractor on July 3, 2026, and that the contractor had not prepared a required quality-assurance plan or an environmental and social management plan.

SOMELEC said the cancellation takes effect from the date the notice was delivered to CTM, and that it reserves the right to apply financial and contractual penalties and to seek compensation for damages linked to the recorded violations. It said the companies in the consortium bear joint responsibility for the contractual obligations and the consequences of the cancellation, each within the scope of its own commitments.

The cancellation follows two fires at separate SOMELEC substations in Nouakchott on August 21 and 22, 2026, which caused power disruptions and outages lasting three to five days in parts of the capital. An independent investigation committee that examined the fires issued its findings in October 2026, attributing contractual responsibility to CTM for using, in its bid, a document that had not been certified by the company it was attributed to — the National Industrial and Mining Company (SNIM) — as well as for changing the cable manufacturer and specifications without proof that required type tests had been carried out, delivering a non-compliant cable, missing deadlines, and not renewing worksite insurance after it lapsed. The committee also found shortcomings by consulting office IRAF in its technical assessment, site supervision and reporting, including approving that the facilities be energized despite reservations it had previously raised. It put the direct cost of the two fires at more than 220 million new Mauritanian ouguiya (about $5.4 million), including roughly 143.9 million ouguiya (about $3.55 million) to repair the two damaged plants.

SOMELEC's cancellation letter linked the decision directly to the accumulation of uncorrected execution failures following the formal warnings. No new date for completing the two new plants or rehabilitating the six existing ones has been announced, and no replacement contractor has been named, leaving the timeline for resuming the work undetermined.