Generation
Ivory Coast, Algeria sign deal for 40MW mobile plant at San Pedro
By: OrePulse
Ivory Coast's state utility CI-Energies and Sonelgaz International, the Algerian group's international arm, signed an agreement in Abidjan on November 17 for a 40-megawatt mobile gas-turbine power plant at San Pedro, in the country's southwest.
CI-Energies director general Amidou Traoré and Sonelgaz International chairman and chief executive Yazid Djellouli signed the deal on the sidelines of the opening of the second edition of SIREXE, the International Extractive Resources and Energy Exhibition, in Abidjan. Ivory Coast's Minister of Mines, Petroleum and Energy, Mamadou Sangafowa-Coulibaly, and his Algerian counterpart for Energy and Renewable Energy, Mourad Adjal, who led Sonelgaz as chief executive from December 2021 to September 2025 both attended the signing.
The San Pedro plant will connect to the 225-kilovolt San Pedro 2 substation, which is still under construction and is meant to be built within three months so it can start operating in the first quarter of 2027. Mobile gas turbines of this kind are modular units that can be installed quickly to shore up a strained power grid.
The agreement also covers mobile substations, transformers, high- and medium-voltage equipment, mobile laboratory trucks to help maintain underground cables, and training for Ivorian engineers at Sonelgaz.
The San Pedro project accounts for part of roughly 100 megawatts of mobile generating capacity envisaged under a wider framework agreement the two countries' energy ministers signed in Abidjan on June 30, 2026.
Ivory Coast's total installed generating capacity now stands at 3,337 MW, after the 390 MW Atinkou power plant came online on November 6, 2026. The government's longer-term target is to reach 11,400 MW of capacity by 2040.