Ghana to start building 1,450 MW state-funded gas plant in December

Ghana to start building 1,450 MW state-funded gas plant in December

By: OrePulse

Ghana plans to begin building a 1,450-megawatt, fully state-funded gas-fired power plant at Kafodzidzi-Abrobeano in the Central Region next month, Finance Minister Cassiel Ato Forson told parliament while presenting the government's 2027 budget. "In December 2026, we will start the construction of a 1,450-megawatt thermal power plant," he said.

The plant is to come online in two stages, with 600 megawatts due by December 2028 and the remaining 850 megawatts following by December 2030. Running it at full capacity will require roughly 150 million standard cubic feet of additional gas a day, which the government intends to draw from the Sankofa and Jubilee fields. Forson did not say who would build the plant, how it would be procured, or whether the gas volumes involved have already been contracted.

The project is part of a wider $2.2 billion energy infrastructure programme the government laid out in the budget, though Forson did not break down how that figure splits across the plant and the other initiatives it covers. Alongside the gas plant, the budget sets out plans for a wholly state-owned 600-megawatt solar plant paired with 2,000 megawatt-hours of battery storage, intended to improve supply and stabilize the grid; no site or timeline was given for the solar project, nor was the battery system's power rating specified. The government also plans to spend $500 million between 2027 and 2030 modernizing the transmission network to cut losses, and to roll out two million prepaid meters aimed at reducing losses further down the distribution chain. Forson said the government intends to have private companies fully running parts of the electricity distribution business under performance-linked contracts by the close of 2027.

The minister tied the new generation capacity to industries he said the government wants to support, including bauxite and manganese processing, steel, cement and agro-processing, as well as the government's 24-Hour Economy programme. He also set a target of cutting the cost of generating electricity from about 16 US cents per kilowatt-hour to 8 cents or less, though he did not say by when that reduction should be achieved.

Forson's budget presentation also disclosed the scale of the financial strain facing Ghana's power sector: an annual shortfall of about $1.4 billion in 2025, and arrears of roughly $1.7 billion owed to independent power producers and fuel suppliers. He framed the planned investments, taken together, as a path toward energy independence and a way to work through those financial difficulties, telling lawmakers, "Mr. Speaker, we will end our dependence on costly emergency power by 2030."

The 1,450-megawatt figure announced this week is larger than the capacity previously associated with the same Kafodzidzi-Abrobeano site: earlier government statements, including last year's budget and a mid-year review presented in July, had referred to a 1,200-megawatt plant planned for the location, a gap of 250 megawatts from the figure disclosed this week. Forson's presentation did not address the change or explain how the larger capacity was arrived at.

Left unanswered in the budget presentation were several other details that would normally accompany a project of this scale: the current amount of power-generation capacity Ghana has available, the size of the shortfall in megawatt terms, whether the December construction start is contingent on reaching financial close or meeting other conditions, and who currently operates the Sankofa and Jubilee gas fields that are meant to supply the new plant.

Whether the 2028 and 2030 completion dates for the two phases of the thermal plant will hold depends on financing, construction progress and gas availability that the budget presentation did not detail, and Forson's remarks offered no contingency plan should either milestone slip. The minister's pairing of the new gas, solar and battery capacity with his pledge to end reliance on costly emergency power by 2030 suggests the government is treating all three elements of the generation build-out as working together toward that single deadline, though the budget presentation did not say what would happen to that timeline if any one piece, such as the solar plant's siting or the battery procurement, were to run behind the thermal plant's own schedule.