Perseus continues to progress Tanzania project to first gold
Four out of the seven carbon-in-leach tanks are now at full height, while the mill installation original-equipment manufacturer has mobilised and started mill installation activities.
The camp administration has been completed.
The project comprises two discrete but adjacent deposits, Nyanzaga and Kilimani.
In February, Perseus completed a revised ore reserve estimate, which now sits at 90.9-million tonnes at 1.38 g/t gold for four-million ounces of gold.
Related Articles
Trending News
Energy Other
TotalEnergies consortium launches South Africa hybrid solar and BESS project...
20 Jul, 2026 10:31
10 min read
Energy Other
DEWA approves 61,183 NOC applications in first half of 2026...
20 Jul, 2026 10:12
23 min read
Base Metals
Africa's Lithium Production Soars, Raising the Stakes for Local Processing...
20 Jul, 2026 10:05
31 min read
Energy Other
Namibia: ReconAfrica Confirms Gas Beneath the Kalahari Desert...
20 Jul, 2026 09:29
33 min read