Perseus continues to progress Tanzania project to first gold
Four out of the seven carbon-in-leach tanks are now at full height, while the mill installation original-equipment manufacturer has mobilised and started mill installation activities.
The camp administration has been completed.
The project comprises two discrete but adjacent deposits, Nyanzaga and Kilimani.
In February, Perseus completed a revised ore reserve estimate, which now sits at 90.9-million tonnes at 1.38 g/t gold for four-million ounces of gold.
Related Articles
Trending News
Energy Markets
Oil prices surge as Houthi, Iraq-based attacks disrupt Saudi export routes...
18 Sep, 2026 18:46
173 min read
Energy Markets
Dangote Refinery launches $1.62bn IPO on Nigerian Exchange...
18 Sep, 2026 18:26
160 min read
Distribution
Oil prices edge lower on easing fears over Saudi supply disruption...
18 Sep, 2026 18:03
151 min read
Mining Other
Atomic Eagle Secures $10.85M Funding Commitment to Advance Zambia and Niger Uranium Projects...
18 Sep, 2026 17:48
165 min read