Perseus continues to progress Tanzania project to first gold
Four out of the seven carbon-in-leach tanks are now at full height, while the mill installation original-equipment manufacturer has mobilised and started mill installation activities.
The camp administration has been completed.
The project comprises two discrete but adjacent deposits, Nyanzaga and Kilimani.
In February, Perseus completed a revised ore reserve estimate, which now sits at 90.9-million tonnes at 1.38 g/t gold for four-million ounces of gold.