Perseus continues to progress Tanzania project to first gold
Four out of the seven carbon-in-leach tanks are now at full height, while the mill installation original-equipment manufacturer has mobilised and started mill installation activities.
The camp administration has been completed.
The project comprises two discrete but adjacent deposits, Nyanzaga and Kilimani.
In February, Perseus completed a revised ore reserve estimate, which now sits at 90.9-million tonnes at 1.38 g/t gold for four-million ounces of gold.
Related Articles
Trending News
Energy Markets
Oil prices rise above $90 as U.S.-Iran tensions fuel Hormuz disruption concerns...
20 Jul, 2026 14:00
68 min read
Metal Markets
Gold prices rise to $4,024.61 as oil-driven inflation concerns persist amid Hormuz tensions...
20 Jul, 2026 13:55
65 min read
Base Metals
Global aluminium output falls 1.5% year-on-year in June, IAI says...
20 Jul, 2026 13:50
56 min read
Energy Other
Egyptian group shortlisted for Oman’s $6bn energy projects...
20 Jul, 2026 13:18
55 min read